Step 1.
It is important that the foundation is setup and poured correctly so that the anchor bolts are in the correct spot.
Step 2.
Primary Framing consists of the I-Beam frames. These members are the first pieces that you will bolt together and fasten to your foundation. Once a few of your frames are up, you can start to bolt the secondary framing to the primary framing.
Step 3.
Secondary Framing consists of the girts and purlins. These members run the length of the building and provide the strength behind the wall and roof sheeting. Once all the secondary framing is in place, you can then fasten the wall and roof sheeting.
Step 4.
Wall and Roof Sheeting attaches using self drilling fasteners. As you install the panels you also install the weather stripping which will keep the building leak free.
Step 5.
Trim and Accessories are installed once all the panels are attached. The trim really finishes off the building and creates a weather tightness seal. Accessories are installed last including the doors, windows and vents.